PLAN COMMISSION MINUTES

July 13, 2006

 

Chairman Ed Sedor called the July 13, 2006 meeting of the Town of Peshtigo Plan Commission to order at 7:00 p.m.

 

Plan Commission members attending were Bruno Brysiewicz, Tim Oestreich, Ed Sedor, Dick Seils, Karen Sylvester and alternate Wendel Johnson. 

 

Absent was Ed Malechuk.

 

Also attending were Leo Krivickas, Town of Peshtigo Building Inspector, Mike Kunesh, Mark Ihlenfeldt and Pete Kretz.

 

Copies of the latest Town of Peshtigo Zoning Ordinance was provided to Seils, Brysiewicz, Johnson and Ihlenfeldt.

 

A motion was made by Seils and seconded by Johnson to approve the agenda as printed.  The motion carried with all in favor.

 

The minutes were not approved as the agenda indicated the minutes of February 9, 2006 needed to be approved while the minutes mailed were dated September 19, 2005.  This matter will be taken up at the next meeting.

 

Presentation by APEX Construction and discussion of the plan for the condominium development at Little River Country Club.

 

The revised plans for the development were discussed. 

 

The driveway permit from Marinette County has already been received.  The Town would like to obtain a copy. 

 

The group wants to be sure that the preliminary plans for the development will meet Town specifications before any Certified Survey maps are completed.

 

The cul-de-sac at the end of the private road has a diameter of 75 feet.  There is concern that fire trucks will have a problem with this and therefore, the group was asked to speak with Fire Chief Clarence Coble.

 

All utilities will be underground. 

 

The soil testing has been completed.  Because each unit will have its own conventional sanitary sewer system, the permits will be obtained on an individual basis prior to construction.  The group intends to construct one or two spec homes with the remainder being built on request of a buyer.  Each building will take approximately 120 days to construct.  If only one unit in a building is sold, the entire building will be constructed but the interior will remain unfinished until the unit is sold. 

 

The Town Building Inspector must be furnished with a Sanitary Sewer Permit and the Zoning Permit before a Town Building Permit can be issued. 

 

Wells will be shared in the double units. 

 

The developer will own the development until 50% of the development is sold at which time it will be turned over to the Condominium Association.

 

The first part of the private road will continue to be owned by Amy and Pete Kretz and the Condo Association will be provided an easement.

 

The group intends to keep as many trees as possible standing through construction, and has stated that erosion control measures will be of primary importance.  Mr. Kretz wants all landscaping within the development to aesthetically blend with the surrounding golf course.    

 

The group would like to close and start construction August 15th.

 

Two of the units are already sold and they have three more parties interested.  Owners of the units will obtain a one year membership to Little River Golf Country Club.

 

The next Plan Commission meeting will be Tuesday, August 1, 2006 at 6:30 p.m. for the public hearing and final recommendation to the Town Board.  All material listed under Sec. 13-1-50(d)(4) must be provided before the scheduled public hearing.

 

A motion was made by Seils and seconded by Oestreich to adjourn at 8:07 p.m.

 

Respectfully submitted,

 

 

 

Karen M. Sylvester